6 questions Basic

ECADEMY test

19 - Prefabricated Pumping Stations

This course test contains 6 questions and can be retaken at any time.

You must answer all questions correctly to pass the test and complete the course.

Start test

Question 6 of 6 Basic

Happy with your answers?

Submit your current answers and get the final test result.

Submit

Test results

Congratulations. You have passed the test and completed the 19 - Prefabricated Pumping Stations

Achieved badges:

Continue training Go to MyECADEMY

Sorry. You did not pass the 19 - Prefabricated Pumping Stations test this time

Correct
Q: Where is the submerged to dry installation placed?
A: In a separate hole next to the old pumping station
Correct
Q: What does an IO 113 sensor module do?
A: It protects the motor
Correct
Q: How are inlet pipes added to the PS.R stations?
A: Added on site with a holedril
Correct
Q: Up to how many pumps can Grundfos Dedicated Controls control?
A: 6
Correct
Q: What does it mean that the CUE frequency converter is pre-programmed?
A: It lets you reduce commissioning time significantly
Correct
Q: Which PS.R features prevent uplift?
A: A shoulder on the sump together with ribs